Technical guide

Tank coating: types, selection by stored product and project steps

Hicham M, P Eng, PMP7 min read

Related solution: Tank & Water Tower Painting

A tank coating is the protection system applied to the walls of a tank: inside, it isolates the steel or concrete from the stored product; outside, it protects against the weather. The right type is chosen in this order: face to protect, stored product and temperature, tank material, then the shutdown window available. The common families are epoxy, novolac epoxy, vinyl ester, polyurea and rubber.

This page gives the overview owners look for before starting a project: which types exist, which one suits which product, and how the job unfolds. It is written for industrial and municipal maintenance managers and project managers in Quebec and Ontario. Residential tanks (home heating oil, private cisterns) are not part of our services.

Interior lining or exterior coating: what is the difference?

The interior lining resists immersion in the stored product; the exterior coating resists the atmosphere, sunlight and splashes. They are two separate systems, with different products, thicknesses and inspections.

  • Interior. It works in permanent immersion, sometimes hot, sometimes under abrasion. The choice depends on the chemistry of the product, and a single pinpoint defect can be enough to perforate the wall. It is verified by holiday testing.
  • Exterior. It protects against atmospheric corrosion and provides colour. It is defined like a structural paint system, by environment category under ISO 12944, with a UV-stable topcoat.
  • Special areas. The underside of the bottom, the area under insulation, the roof and the fluctuating water level zone each have their own corrosion mechanisms and need specific attention.

Our tank and water tower painting service handles both faces, and the tank lining page describes interior solutions.

What are the main types of tank coating?

Five families cover most industrial tanks. Each has a field where it excels and a field where it does not fit.

  • Epoxy. Versatile, it suits water, many hydrocarbons and mildly aggressive solutions. It is the starting point of many systems.
  • Novolac epoxy. More highly cross-linked, it resists acids, solvents and heat better than ordinary epoxy.
  • Vinyl ester. Often reinforced with flakes or glass fibre, it is selected for acids and oxidizing environments.
  • Polyurea. A flexible hot-sprayed membrane with a very fast set, useful for cracked concrete and short return-to-service windows.
  • Rubber. Sheets bonded and then vulcanized, for acids and abrasive slurries. See our rubber lining service.

The detailed comparison of these systems, with selection criteria, immersion testing and the treatment of details, is in our industrial tank lining selection guide. Only the summary is repeated here.

Which coating for which stored product?

The stored product, its concentration and its temperature decide the coating family. The table below gives the usual directions; chemical resistance is always confirmed with the manufacturer's tables for the actual product, concentration and temperature.

Stored productUsual directionsPoint to validate
Potable waterEpoxy or polyurea listed for potable water contactNSF/ANSI/CAN 61 listing, AWWA D102 requirements for steel
Fire water or process waterImmersion-grade epoxyWater quality, fluctuating level zone, cathodic protection if any
Fuels, diesel, oilsEpoxy or novolac epoxy depending on the productWater at the tank bottom, API 652 for the bottom
AcidsVinyl ester, novolac epoxy or rubberType of acid, concentration, temperature
Caustic and alkaline productsSuitable epoxyService temperature
WastewaterHigh-build epoxy or polyurea, on concrete or steelHydrogen sulphide in the gas phase
Abrasive slurriesRubber or a filled wear-resistant coatingParticle size and velocity

Each case has its own detailed article: potable water tank coating and NSF/ANSI/CAN 61, fuel and diesel tank coatings, sulfuric acid tank lining and wastewater concrete corrosion.

Steel or concrete tank: what changes?

The material changes the preparation, the primer and the defects to watch, not the selection logic. Steel corrodes; concrete cracks, lets moisture through and breaks down under acid attack.

On steel, preparation is abrasive blasting to the specified grade, with welds and sharp edges dressed first. The coating is continuous and is checked by holiday testing, with a high-voltage spark tester or a wet sponge depending on thickness.

On concrete, repairs come first: cracks, honeycombing, attacked areas. The surface is then mechanically prepared to open the pores, substrate moisture is checked, and a primer and a resurfacer close the bugholes before the membrane. Joints and moving cracks receive a flexible treatment. Concrete exposed to hydrogen sulphide needs an acid-resistant system, not just paint.

In both cases, the coating is part of a protective coatings system that includes preparation, inspection and prior repairs.

How does a tank coating project unfold?

A project runs in seven steps, from inspection to return to service. The inside of a tank is a confined space: safety and ventilation shape the whole job.

  • Inspection and survey. Condition of the wall and the existing coating, steel thickness, stored product, temperature, failure history.
  • System selection. Coating family, thickness, preparation grade, inspections and acceptance criteria, written into a specification.
  • Taking out of service. Draining, cleaning, gas-freeing, lockout and confined space entry permit, under the owner's responsibility and procedures.
  • Preparation. Abrasive blasting, dust removal, soluble salt testing where required. Our article on tank interior abrasive blasting describes this step.
  • Application. Ambient conditions controlled by dehumidification or heating as needed, coats applied within recoat windows.
  • Inspection. Dry film thickness, holiday test, adhesion where specified, repair of defects.
  • Cure and return to service. The time before filling comes from the data sheet and the temperature; it cannot be shortened.

What moves the price and duration of a project?

Price and duration depend mostly on area, starting condition, access and the system chosen. No figure can be given without a visit and a survey.

  • Size and geometry. Height, fixed or floating roof, baffles, coils, internal structures.
  • Initial condition. Existing coating to remove, corrosion, steel or concrete repairs to complete before coating.
  • Product and system. A thick reinforced system takes more coats and time than a thin epoxy.
  • Access and confined space. Scaffolding, ventilation, attendants, rescue.
  • Season. Cold-weather work adds heating and dehumidification.
  • Shutdown window. A short outage can justify a fast-curing product or several shifts.

These factors are detailed, without figures, in our article on tank lining and coating cost.

How do you get a recommendation and a quote?

Provide the stored product, its concentration, its temperature, the dimensions, the material and a few photos of the current condition. With that, we propose a system, a work sequence and the associated inspections.

Our tank painting and coating service covers interiors and exteriors, on steel and on concrete. Our crews and qualified subcontractors work out of LaSalle, including in Bécancour, in Montreal and in Ontario. Write to us through the request a quote form: pricing on consultation, reply within 24 business hours.

Frequently asked questions

What is the best coating for a tank?

There is no single one. The best is the one whose resistance to the stored product, its concentration and its temperature is confirmed by the manufacturer, and that can be applied properly within the shutdown window available.

Can a tank be coated without emptying it?

Not the interior: the lining is applied to a clean, dry, accessible wall. The exterior, on the other hand, is usually repainted in service, with precautions related to wall temperature and condensation.

Does the same coating suit steel and concrete?

The same family can suit both, but not the same system. Concrete needs its own repairs, primer and resurfacing, as well as treatment of cracks and joints.

How is a tank lining verified?

By measuring dry film thickness, by holiday testing the whole surface and by visually examining welds, edges and nozzles. Defects found are repaired and tested again before filling.

#tank coating#storage tank#tank lining#tank painting#corrosion protection
HM

Hicham M, P Eng, PMP

Engineer and project manager (PMP) at Induscoat. Over 16 years of experience in industrial coatings, composite repairs and wear protection on mining, energy and petrochemical sites in Canada and internationally.

Related articles

Technical guide

Industrial tank coating: how to choose the internal lining for the product you store

The right tank lining is decided by the service, not by the product catalogue. This guide walks through the selection criteria (stored product, temperature, vacuum, abrasion, cleaning, potable water and food contact), compares the main lining families, and explains how resistance charts, immersion tests and weld details turn a shortlist into a specification.

Hicham M, P Eng, PMP
10 min
Economics

Tank lining and coating cost: the 8 factors behind the price of interior and exterior tank work

The cost of lining or coating a tank depends on eight factors: interior or exterior, stored product, steel or concrete condition, soluble salts, confined space, ventilation and dehumidification, inspection and downtime. This guide explains how each one weighs and what to provide for an accurate quote.

Hicham M, P Eng, PMP
7 min
Technical guide

Fuel and diesel tank coatings: interior lining and exterior protection

A fuel tank corrodes mostly at the bottom, where water settles, and on the outside from the weather. This guide explains how to choose an interior lining compatible with hydrocarbons, deal with bottom water, control static electricity and prepare gas-freeing and confined space entry.

Hicham M, P Eng, PMP
7 min
Guide

Potable water tank coating: NSF/ANSI/CAN 61 and AWWA D102

The interior of a potable water tank is not repainted like an ordinary structure. The system must be listed to NSF/ANSI/CAN 61, applied per AWWA D102 and the conditions of its listing, and cured before disinfection and return to service. This guide explains the requirements for the interior, the exterior and inspection.

Hicham M, P Eng, PMP
7 min