Practical guide

Intumescent paint for steel: application on a structural frame and inspection

Hicham M, P Eng, PMP7 min read

Related solution: Intumescent Coatings for Steel

Intumescent paint is applied to prepared steel coated with a compatible primer, most often by airless spray, in one or several coats until it reaches the dry film thickness set for each section. That thickness comes from the manufacturer's tables, built from fire resistance tests to CAN/ULC-S101. An approved topcoat protects it, and every member is measured and recorded.

Under heat, the film swells into an insulating carbon foam that delays the heating of the steel. Its performance depends entirely on what was applied, member by member. This guide follows the job in order, for project managers, general contractors and managers of industrial and commercial buildings in Quebec and Ontario. Who sets the fire-resistance rating and what a listed design is are covered in our article on intumescent coating fire ratings.

How is intumescent paint applied to a steel frame?

It is applied in five stages: steel preparation, primer, intumescent coats, topcoat, inspection. The order does not change, whether the work is done in the shop before erection or on site on the erected frame.

  • Preparation. The steel is degreased, then blast cleaned or power tool cleaned to the grade required by the primer data sheet.
  • Primer. An anticorrosion primer accepted by the intumescent manufacturer is applied at the permitted thickness, then measured.
  • Intumescent. The product is applied by airless spray on large surfaces, by brush or roller for touch-ups and tight areas. Wet thickness per coat is limited to avoid sags; total thickness is built in several passes if needed, respecting drying times.
  • Topcoat. An approved topcoat is applied once the intumescent is dry through.
  • Inspection. Dry film thickness is measured member by member and recorded.

In the shop, conditions are controlled, but handling and erection damage the film: field touch-ups must be planned. On site, nearby work must be protected from overspray and the job coordinated with other trades. Our comparison of shop vs field painting for new steel helps split the work.

Which primer goes under intumescent paint?

A primer that appears on the intumescent manufacturer's list of accepted primers, applied within the thickness range that list gives. The system was fire tested with certain primers: another primer can soften under heat and let the foam fall off.

Four situations come up on a job:

  • New bare steel. The simplest case: choose a primer from the list and prepare the steel to its data sheet.
  • Steel delivered with a shop primer. The product and its thickness must be known. If it is not accepted or is unknown, a compatibility and adhesion test is done, an accepted tie coat is applied, or the primer is removed.
  • Galvanized steel. The surface needs preparation and a tie primer specific to zinc, validated by the manufacturer.
  • Zinc-rich primer. It is accepted only for some products and under some conditions; the manufacturer's documentation decides.

A primer that is too thick is also a defect: it can exceed the limit allowed by the system. Preparation and priming fall under our steel structure painting service.

What thickness is needed for each section and rating?

Thickness depends on three inputs: the massivity of the section, the fire resistance duration required and the role of the member (beam, column, hollow section). It is read from the manufacturer's tables, drawn from tests to CAN/ULC-S101; it is not worked out by simple proportion and cannot be carried over from one product to another.

InputEffect on thicknessWhere to find it
Section massivity (W/D ratio or section factor)A thin, light section heats faster and needs more thickness than a heavy oneSection tables, calculation per member
Fire resistance duration requiredThe longer the duration, the greater the thicknessCode requirements and project documents
Member type and exposed facesBeam under a slab, column exposed on all faces, hollow section: separate tablesManufacturer's listed design
ProductEach product has its own tablesData sheet and listing documentation
Limits of the designMinimum and maximum sizes covered by the testsListed design

The result is a project-specific thickness schedule: each framing mark receives its dry film thickness. This schedule is prepared before mobilization and validated by the project designer. A section outside the limits of the design is flagged before the job, not during inspection.

Is a topcoat needed, and which one?

Yes in most cases: the topcoat protects the intumescent from moisture, dirt, light impact and UV, and provides colour. It must be one of the topcoats approved by the manufacturer, and its thickness is limited so it does not hinder expansion.

  • Dry, concealed interior. Some products need no topcoat; the data sheet says so.
  • Humid or visible interior. An approved topcoat is applied, for durability and appearance.
  • Exterior or weather exposure. A product designed for that exposure is required, with its mandatory topcoat. A dry-interior product is not suitable.

The topcoat is applied only over an intumescent that is dry through. In an industrial setting, the full system is chosen with the same criteria as a protective coatings system: environment, maintenance, future access.

How is the application inspected?

It is inspected at three moments: before, during and after application. The aim is to prove that each member carries the right product, over the right primer, at the right thickness.

  • Before. Checking preparation, primer identity and thickness, ambient conditions (temperature, relative humidity, dew point) and product batches.
  • During. Measuring wet film thickness with a gauge, to correct right away. The link between wet and dry film is explained in our article on wet and dry film thickness.
  • After. Measuring dry film thickness with an electromagnetic gauge, on the flanges and web of each member, after deducting the primer. The measurement plan follows the specification or a recognized practice such as AWCI Technical Manual 12-B.
  • Appearance. Looking for sags, cracks, misses and damage.

The handover file gathers the thickness schedule, the readings per member, the data sheets, the batches and the ambient conditions. Our coating inspection service can carry out this verification.

What errors make intumescent paint fail?

Most failures come from a gap between what was fire tested and what was applied. These errors come up most often:

  • Primer not accepted or too thick. The system is no longer the one in the listed design.
  • Uniform thickness across the whole frame. Light sections are then under-protected and heavy sections overloaded.
  • Coats too thick or too close together. Sags, shrinkage cracks and incomplete drying.
  • Application in cold or humid weather. Water-based products in particular dry poorly; heating and ventilation are needed.
  • Forgetting to deduct the primer. The actual intumescent thickness is overestimated.
  • Topcoat missing, unsuitable or too thick. The intumescent degrades or expands poorly.
  • Damage by other trades. Fasteners, welds and cable runs after acceptance, with no recorded repair.

When the required thickness becomes very high or the environment is severe, another solution may fit better: see our comparison of cementitious vs intumescent fireproofing.

How do you get intumescent paint applied to your frame?

Prepare the project by gathering the framing drawings, the fire resistance required, the condition of the steel (bare, primed, galvanized) and the planned exposure. With that, we establish the system, the thickness schedule and the work sequence. In an occupied building, the job is organized by zones, as for warehouse steel frame painting in service.

Our intumescent coatings service covers preparation, primer, application, topcoat and the inspection file. Our crews and qualified subcontractors work out of LaSalle, including in Laval, in Montreal and in Ontario. Send the drawings and a few photos through the request a quote form: pricing on consultation, reply within 24 business hours.

Frequently asked questions

Can intumescent paint be applied over steel that is already painted?

Only if the existing paint is identified, adherent and accepted by the intumescent manufacturer, or after a compatibility test. Otherwise it is removed and the steel receives a primer from the list.

How many coats are needed?

As many as it takes to reach the dry film thickness in the schedule without exceeding the wet thickness allowed per coat. A light section with a long required duration needs more passes than a heavy one.

Does intumescent paint protect steel from corrosion?

No, that is not its role. Corrosion protection comes from the primer, and the topcoat protects the intumescent itself. The full system is defined according to the environment.

Who verifies the applied thickness?

The applicator measures and records during the work. The project inspector or a designated third party then reviews the records and takes independent readings, at the request of the owner or the authority having jurisdiction.

#intumescent paint#structural steel#fire resistance#application#inspection
HM

Hicham M, P Eng, PMP

Engineer and project manager (PMP) at Induscoat. Over 16 years of experience in industrial coatings, composite repairs and wear protection on mining, energy and petrochemical sites in Canada and internationally.

Related articles

Technical guide

Intumescent coatings: how thickness and fire rating are determined

The thickness of an intumescent coating is not chosen on site: it follows from the fire-resistance rating the code requires, a listed design and the massiveness of each steel section. This guide explains who decides what, the CAN/ULC-S101, UL 263 and UL 1709 standards, thickness control, coat compatibility and inspection.

Hicham M, P Eng, PMP
7 min
Comparison

Cementitious fireproofing vs intumescent coating: how to choose

Cementitious fireproofing and intumescent coatings both protect steel from fire, but not under the same conditions. This guide compares the two families by fire type (cellulosic or hydrocarbon), appearance, thickness, risk of corrosion under fireproofing and ease of repair in a plant.

Hicham M, P Eng, PMP
7 min
Practical guide

Painting the steel frame of an operating warehouse without shutting down

Repainting the beams, columns, purlins and bracing of a warehouse that stays open takes a method: protect racking and stock, move aerial lifts between aisles, control dust and overspray, prepare without blasting and work zone by zone around operating hours. This guide explains how.

Hicham M, P Eng, PMP
7 min
Comparison

Painting new steel: in the shop or in the field?

Painting new structural steel in the shop gives more consistent preparation, but handling, erection and connections require touch-up in the field. This guide compares both approaches, explains how to treat connections, when to apply the topcoat on site and which inspections to plan.

Hicham M, P Eng, PMP
7 min